Update: South Bay Construction Schedule

What’s happening with the South Bay retail center? Below is a construction schedule update dated December 5, 2017 from Keith Hague, Vice President of Construction & Development, at EDENS (21 Custom House Street, Suite 450, Boston, MA 02110. Phone: 617.369.6609). Interested residents can read about the South Bay retail center at the Edens site, and/or follow Edens on Facebook, Twitter, and YouTube.
.

CONSTRUCTION MILESTONES

December, 2017:

  • First retail tenant openings
    • Ulta: Now open
    • AMC: December 15th Star Wars release. Get your tickets online now! Theatre may open a few days prior
    • Nike: December 8th
    • Loft Outlet: December 8th
    • Starbucks: TBD
  • Boston Street & West Howell Street: Underground utilities complete
  • Enterprise Street (Lucy St. to Mass Ave): Complete

Spring 2018:

  • Start remaining off-site roadway improvements (W. Howell, Jan Karski Way to District Ave, Connector Road between Hotel and Scrub a Dub.)

Summer 2018:

  • Residential Building D and ground floor retail tenant openings
  • Complete off site roadway improvements (W. Howell, Jan Karski Way to District Ave, Connector Road between Hotel and Scrub-a-Dub.)

Fall 2018:

  • Residential Building C and ground floor retail tenant openings
  • Start construction of Hotel E Building
  • Completion of Jan Karski Way improvements from District Ave to Enterprise Street
  • Completion of Enterprise improvements from Jan Karski Way to Lucy Street

Summer 2019:

  • Completion of Hotel E Building

Tenant Announcements

  • JP Licks, Carter’s, Forever 21 Red, MidiCi (Neapolitan pizza), Wahlburgers, Gyu-Kaku (Japanese BBQ), Title Boxing & Chipotle
  • Buildings A & B: Four remaining tenant spaces still to be announced
  • Buildings C&D: Six remaining tenant spaces still to be announced